A uniform cable of massand lengthis placed on a horizontal surface such that itspart is hanging below the edge of the surface. To lift the hanging part of the cable upto the surface, the work done should be:
Options:
Answer:
A
Solution:
Mass of the part hanging is. Centre of mass of this part liesdistance from the surface.
Work done in lifting the hanging part to surface is