A train takes 2 minutes to acquire its full speed 60 kph from rest and 1 minute to come to rest from the full speed. If somewhere between two stations 2 km of the track is under repair with the speed limited to 20 kph, find the late running of the train on account of the repair work. (Answer in seconds.)

Answer:
280
Solution:

Acceleration

(2 min to 60 kph); retardation

(1 min from 60 kph). Slowing 60 → 20 kph: 40 s over
;
2 km at 20 kph: 360 s; regaining 20 → 60 kph: 80 s over 889 m. Affected stretch

covered in

480 s; at full 60 kph the same stretch takes

s. Late running