Physics - Kinematics Question with Solution | TestHub
PhysicsKinematics1-DMedium2 minQB
PhysicsMediuminteger
A train takes 2 minutes to acquire its full speed 60 kph from rest and 1 minute to come to rest from the full speed. If somewhere between two stations 2 km of the track is under repair with the speed limited to 20 kph, find the late running of the train on account of the repair work. (Answer in seconds.)
Answer:
280
Solution:
Acceleration
(2 min to 60 kph); retardation
(1 min from 60 kph). Slowing 60 → 20 kph: 40 s over
;
2 km at 20 kph: 360 s; regaining 20 → 60 kph: 80 s over 889 m. Affected stretch
covered in
480 s; at full 60 kph the same stretch takes
s. Late running
Stream:JEESubject:PhysicsTopic:KinematicsSubtopic:1-D
⏱ 2mℹ️ Source: QB
Doubts & Discussion
Loading discussions...
